CUADRO NRO. 87 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Página 2/2 |
|
DIRECCION NACIONAL DE VIALIDAD. ORDENAMIENTO DE LOS PROYECTOS POR NIVEL DE EJECUCION |
PROGRAMA 21: CONSERVACION MEJORATIVA, MEJORAMIENTO Y RECONSTRUCCION |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DATOS DE OBRA |
AVANCE FINANCIERO (miles de pesos) |
|
|
CERTIFICACION |
Avance Físico |
INICIO |
FIN |
|
Sp |
Py |
RUTA |
Tramo |
Seccion |
Expte |
Cod. ob. |
Long |
Fuente |
Cod. ob. |
Tipo de obra |
Long |
Inv Total |
Acum 95 |
Credito31/12/96 |
Dev.31/12/96 |
Arrastre 95/96 |
1 Trim |
2 Trim |
3 Trim |
Septiembre |
Octubre |
Noviembre |
4 Trim |
Total 96 |
Año 96 |
Total |
Real |
Real o Tent. |
ESTADO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
20 |
9 |
Limite con Salta/Jujuy - Emp.R.N.°66 |
El Carmen - Alto Comedero |
1854-L-94 |
|
|
BIRF1A |
|
Reconstruc. total |
20 |
4,832 |
285 |
0 |
0 |
|
|
|
|
|
|
|
|
|
0% |
6% |
23/06/95 |
23/01/97 |
6 |
1 |
19 |
26 |
Emp. R.N. N° 3 - Emp. R.P. N° 20 |
(Km.0 - Km.43) |
1832-L-94 |
|
|
BIRF1A |
|
Refuerzos de 0,05 m. |
43 |
3,644 |
|
57 |
57 |
|
|
|
|
|
|
|
|
|
7% |
7% |
15/03/96 |
15/03/97 |
6 |
3 |
13 |
143 |
Lte. c/La Pampa - Cochicó |
(Km.304 - Km.488) |
4509-L-94 |
|
|
BID |
|
Reconstruc. y ensanche |
32 |
5,739 |
490 |
2,500 |
674 |
|
|
|
|
|
|
|
|
|
11% |
19% |
23/05/95 |
23/05/97 |
6 |
1 |
26 |
25 |
Emp.R.N.N°3-Minas Paraná (I y II Sec) |
(Km.20 - Km.57) |
4777-L-94 |
|
|
BIRF1A |
|
Bacheo y Refuerzos 0.06 m. |
36 |
3,246 |
214 |
665 |
665 |
|
|
|
|
|
|
|
|
|
13% |
20% |
4/09/95 |
4/03/97 |
6 |
1 |
34 |
3 |
Lago Escondido - Rancho Hambre |
Secciones Varias |
2624-L-95 |
|
|
FTN |
|
Enripiado |
10 |
165 |
|
30 |
0 |
|
|
|
|
|
|
|
|
|
33% |
33% |
25/03/96 |
25/06/96 |
6 |
1 |
16 |
237 |
Arroyito - Arroyo La Teresa |
Km. 1270 - Km. 1417 |
4502-V-94 |
|
|
BIRF1B |
|
Bacheo y Lechada |
147 |
5,555 |
|
850 |
845 |
|
|
|
|
|
|
|
|
|
36% |
36% |
12/04/96 |
12/07/97 |
6 |
5 |
21 |
123 |
Emp. R.P. N° 27 - Emp. R.N. N° 12 |
(Km.0 - Km.31) |
4946-L-94 |
|
|
BIRF1A |
|
Reconstruc. total |
31 |
6,238 |
|
1,849 |
1,849 |
|
|
|
|
|
|
|
|
|
37% |
37% |
3/04/96 |
3/08/97 |
6 |
5 |
7 |
12 |
Emp.R.Prov.N 7 - Acc.a La Paz |
(534-601) |
308-L-93 |
|
|
BIRF1B |
|
Refuerzos 0,05 m. |
67 |
4,658 |
|
511 |
511 |
|
|
|
|
|
|
|
|
|
38% |
38% |
28/08/96 |
28/08/98 |
6 |
EJECUCION MENOR A 50% |
|
|
|
|
|
|
|
|
|
|
386 |
34,077 |
989 |
6,463 |
4,602 |
|
|
|
|
|
|
|
|
|
22% |
25% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
21 |
3 |
Lte.c/Bs.As.-Acc. Pto. San Antonio Este |
Prog. 963 - Prog. 1114 |
1876-L-94 |
|
|
BIRF1B |
|
Lechada |
152 |
2,842 |
|
1,100 |
1,097 |
|
|
|
|
|
|
|
|
|
56% |
56% |
26/03/96 |
26/03/97 |
6 |
4 |
16 |
34 |
Emp. R.N. N° 81 - General Mosconi |
(Km.1398 - Km.1431) |
1882-L-94 |
|
|
BIRF1B |
|
Lechada asfáltica |
33 |
1,301 |
21 |
756 |
755 |
|
|
|
|
|
|
|
|
|
58% |
60% |
14/11/95 |
14/12/96 |
9 |
2 |
36 |
9 |
Autopista San Nicolas - Rosario |
Reparacion de dos puentes s/A. Saladillo |
432-L-93 |
|
|
FTN |
|
Reparación 2 Puentes. |
|
1,278 |
734 |
240 |
129 |
|
|
|
|
|
|
|
|
|
10% |
68% |
23/08/93 |
13/12/97 |
6 |
2 |
18 |
35 |
Arroyo El Gato - Emp.R.N.Nš8 |
A° El Gato |
1815-L-94 |
|
|
FTN |
|
Adecuac. integral del puente. |
|
287 |
|
210 |
0 |
|
|
|
|
|
|
|
|
|
70% |
70% |
10/05/96 |
10/12/96 |
6 |
5 |
54 |
S/N° |
Puente Gral . Belgrano |
Corrientes - Chaco |
12988-Vs-89 |
|
|
ESPAÑA |
|
Reemplazo de Obenques |
|
9,736 |
17 |
2,000 |
2,000 |
|
|
|
|
|
|
|
|
|
72% |
73% |
13/02/95 |
13/02/97 |
6 |
1 |
23 |
237 |
Arroyo Carbón - Lte. c/ Río Negro |
(Km.1600 - Km.1627) |
1874-L-94 |
|
|
BIRF1A |
|
Refuerzos de 0.07 m. |
27 |
1,944 |
6 |
965 |
964 |
|
|
|
|
|
|
|
|
|
73% |
73% |
4/10/95 |
4/12/96 |
6 |
EJECUCION ENTRE 50% y 75% |
|
|
|
|
|
|
|
|
|
|
212 |
17,388 |
778 |
5,271 |
4,946 |
|
|
|
|
|
|
|
|
|
64% |
69% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
29 |
7 |
San Martín - Guaymallén |
(997-1042) |
358-L-93 |
|
|
BIRF1B |
|
Reacond.Banq. y Lechada asf. |
45 |
1,995 |
1,140 |
800 |
267 |
|
|
|
|
|
|
|
|
|
20% |
77% |
1/11/93 |
18/01/97 |
6 |
1 |
17 |
237 |
Arroyo La Teresa - Confluencia |
Km. 1417 - Km. 1563 |
4503-V-94 |
|
|
BIRF1B |
|
Bacheo.Lech.Asf. y obras compl. |
146 |
6,716 |
346 |
2,739 |
2,739 |
|
|
|
|
|
|
|
|
|
72% |
77% |
14/09/95 |
14/12/96 |
6 |
4 |
43 |
60 |
Lte. c/La Rioja - Tinogasta |
(1251-1321) |
262-L-93 |
|
|
BIRF1B |
|
Bacheo y Sellado |
70 |
1,409 |
722 |
362 |
362 |
|
|
|
|
|
|
|
|
|
29% |
80% |
14/10/93 |
14/03/96 |
10 |
5 |
1 |
14 |
Emp.R.Nac.N° 117 - Emp.R.P.N° 40 |
(496-709) |
277-L-93 |
|
|
BIRF1C |
|
Bacheo,Alcant. y Repaviment. |
214 |
4,714 |
2,904 |
1,126 |
1,126 |
|
|
|
|
|
|
|
|
|
20% |
81% |
22/10/93 |
22/05/96 |
6 |
5 |
15 |
89 |
Lte.c/Santiago del Estero - Gral. Pinedo (A) |
(Km.263 - Km.311) |
1830-L-94-A |
|
|
BIRF1A |
|
Bacheo y Repavimentacion |
49 |
4,847 |
|
3,210 |
3,093 |
|
|
|
|
|
|
|
|
|
82% |
82% |
27/03/96 |
30/03/98 |
6 |
2 |
27 |
3 |
Pedro Luro-Stroeder (Prog. 779 - Prog. 882) |
(Km.779 - Km.882) |
4779-L-94 |
|
|
BIRF1A |
|
Bacheo y refuerzo |
103 |
7,780 |
536 |
5,234 |
5,234 |
|
|
|
|
|
|
|
|
|
82% |
89% |
8/08/95 |
8/01/97 |
6 |
1 |
45 |
25 |
Trelew - Las Chapas |
(57-146,7) |
301-L-93 |
|
|
FTN |
|
Bacheo y Lechada |
90 |
5,129 |
4,075 |
1,054 |
855 |
|
|
|
|
|
|
|
|
|
16% |
96% |
29/11/93 |
30/11/96 |
6 |
1 |
1 |
Vs |
Rutas nac. n°3, 40, 281, 288 |
|
1692-Vs-93 |
|
|
FTN |
|
Aplic. de microaglomerado |
340 |
28,031 |
14,773 |
12,580 |
11,677 |
|
|
|
|
|
|
|
|
|
44% |
96% |
11/03/93 |
11/05/97 |
6 |
4 |
27 |
38/60 |
Lte.c/La Rioja-Cat. /Emp.R.N.38-Emp.R.N.62 |
(Km.506 -Km. 580) |
4504-V-94 |
|
|
BIRF1A |
|
Refuerzos 0,05 m. |
74 |
6,717 |
445 |
5,451 |
5,451 |
|
|
|
|
|
|
|
|
|
90% |
97% |
11/09/95 |
15/11/97 |
6 |
4 |
11 |
34 |
Lte.c/Jujuy - Emp.R.N.50 |
(1287 - 1329) |
403-L-93 |
|
|
BIRF1B |
|
Tratamiento Doble |
42 |
1,178 |
309 |
754 |
754 |
|
|
|
|
|
|
|
|
|
72% |
98% |
12/02/94 |
12/02/96 |
6 |
3 |
32 |
7 |
Cto. Fron. - Lte. c/Chile (Tunel Inter. Carac |
Tunel Int. Caracoles |
1808-L-94 |
|
|
FTN |
|
Reparac. túnel y calz. pav. artic. |
2 |
2,387 |
2,205 |
562 |
562 |
|
|
|
|
|
|
|
|
|
6% |
98% |
20/02/95 |
20/11/97 |
6 |
4 |
25 |
64 |
Santiago del Estero - Empalme R.P. Nš24 - (A) |
(Km.12.3 - Km.59.3) |
1904-L-94-A |
|
|
BIRF1B |
|
Tratamiento Doble |
47 |
4,706 |
736 |
4,655 |
4,652 |
|
|
|
|
|
|
|
|
|
84% |
99% |
21/06/95 |
21/06/97 |
6 |
2 |
17 |
38 |
Cruz del Eje-Lte.c/La Rioja |
Puente s/Rio Pichanas |
1814-L-94 |
|
|
FTN |
|
Ensanche puente. |
|
355 |
|
350 |
350 |
|
|
|
|
|
|
|
|
|
99% |
99% |
4/03/96 |
4/12/96 |
6 |
3 |
8 |
40N |
Huaco - Lte. c/La Rioja |
(Km.352 - Km.414,2) |
1888-L-94 |
|
|
FTN |
|
Tratamiento doble y Obras Compl. |
62 |
5,169 |
1,895 |
3,610 |
3,609 |
|
|
|
|
|
|
|
|
|
63% |
100% |
15/07/95 |
9/12/96 |
6 |
1 |
39 |
3 |
Río Pipo - Bahía Lapataia |
Secciones Varias |
2625-L-95 |
|
|
FTN |
|
Enripiados Parciales |
16 |
112 |
|
60 |
0 |
|
|
|
|
|
|
|
|
|
100% |
100% |
25/03/96 |
25/06/96 |
6 |
EJECUCION MAYOR A 75% pero NO FINALIZADAS |
|
|
|
|
|
|
|
|
|
|
1,300 |
81,245 |
30,086 |
42,548 |
40,732 |
|
|
|
|
|
|
|
|
|
55% |
92% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
28 |
50 |
Oran - Lte.c/Bolivia |
Pte. s/R. Pescado |
1885-L-94 |
|
|
FTN |
|
Construcción de defensas |
|
259 |
|
207 |
207 |
|
|
|
|
|
|
|
|
|
87% |
87% |
5/02/96 |
5/09/96 |
7 |
3 |
3 |
7 |
Potrerillos - Aš El Taure |
(1097-1191,4) |
359-L-93 |
|
|
BIRF1A |
|
Tratamiento doble y Obras Compl. |
94 |
3,710 |
2,906 |
756 |
756 |
|
|
|
|
|
|
|
|
|
18% |
97% |
21/12/93 |
22/04/96 |
7 |
5 |
13 |
18 |
A° Moreira - Villaguay (II Sección) |
(Km.123 - Km.150) |
1838-L-94 |
|
|
BIRF1A |
|
Refuerzos. 0,08 m. |
27 |
3,034 |
2,261 |
1,490 |
1,484 |
|
|
|
|
|
|
|
|
|
22% |
97% |
4/05/95 |
4/03/96 |
7 |
3 |
11 |
79 |
Santa Rita de Catuna - Chamical |
(Km. 176-Km. 247) |
1863-L-94 |
|
|
FTN |
|
Bacheo y Lechada |
71 |
949 |
|
946 |
945 |
|
|
|
|
|
|
|
|
|
97% |
97% |
29/01/96 |
30/12/96 |
7 |
3 |
16 |
7 |
Punta de Vacas - Las Cuevas |
(Km.1204 - Km.1235) |
1866-L-94 |
|
|
BIRF1A |
|
Reconstrucción. Losas |
31 |
1,093 |
373 |
901 |
901 |
|
|
|
|
|
|
|
|
|
65% |
99% |
14/08/95 |
14/06/96 |
7 |
5 |
2 |
16 |
Pampa del Infierno-Lte.c/Sgo. del Est. |
(262-319) |
285-L-93 |
|
|
FTN |
|
Bacheo y refuerzo |
57 |
7,121 |
3,614 |
3,708 |
3,708 |
|
|
|
|
|
|
|
|
|
48% |
99% |
28/12/93 |
28/10/96 |
7 |
2 |
26 |
3 |
Stroeder - Patagones |
(Km.882 - Km.963) |
4507-L-94 |
|
|
BIRF1A |
|
Bacheo y refuerzo de 0,05 |
81 |
6,781 |
1,974 |
6,312 |
6,312 |
|
|
|
|
|
|
|
|
|
70% |
99% |
24/07/95 |
24/07/96 |
7 |
5 |
14 |
12 |
Lte. c/Entre Ríos - Goya (I Sección) |
(Km.647 -Km.750) |
1822-L-94 |
|
|
BIRF1B |
|
Lechada Asfaltica |
103 |
1,492 |
41 |
1,357 |
1,357 |
|
|
|
|
|
|
|
|
|
97% |
99% |
21/09/95 |
21/09/96 |
7 |
2 |
23 |
35 |
Nueva Roma - San Germán |
(Km.50 - Km.81) |
4506-V-94 |
|
|
BIRF1A |
|
Bacheo y Refuerzos de 0,05 m. |
31 |
2,383 |
1,138 |
1,735 |
1,735 |
|
|
|
|
|
|
|
|
|
52% |
100% |
10/07/95 |
10/03/96 |
7 |
5 |
23 |
127 |
Emp. R.N. N° 12-Sauce de Luna (IISecc) |
(Km.102,5 - Km.141,1) |
1842-L-94 |
|
|
BIRF1A |
|
Bacheo y repav. 0.07 m. |
39 |
4,728 |
|
4,843 |
4,843 |
|
|
|
|
|
|
|
|
|
100% |
100% |
12/02/96 |
17/07/97 |
7 |
4 |
2 |
16 |
Lte. con Chaco - El Cabure |
(319-388) |
449-L-93 |
|
|
FTN |
|
Bacheo y Tratamiento Doble |
69 |
3,106 |
2,910 |
|
|
|
|
|
|
|
|
|
|
|
6% |
100% |
14/10/93 |
14/10/95 |
7 |
1 |
4 |
3 |
Trelew - Acc.a Camarones (II Seccion) |
(1538-1611) |
291-L-93 |
|
|
BIRF1A |
|
Bacheo y Lechada |
73 |
5,743 |
4,564 |
1,201 |
1,201 |
|
|
|
|
|
|
|
|
|
21% |
100% |
18/11/93 |
25/02/96 |
7 |
2 |
21 |
228 |
Necochea - Emp. R. Prov. 75 |
(Km.32 - Km.55) |
4505-V-94 |
|
|
BIRF1A |
|
Bacheo y Refuerzos de 0,05 m. |
23 |
1,782 |
165 |
1,743 |
1,743 |
|
|
|
|
|
|
|
|
|
91% |
100% |
26/07/95 |
30/03/96 |
8 |
2 |
25 |
9 |
Cordoba - Jesús Maria |
(Km.709 - Km.751) |
1813-L-94 |
|
|
FTN |
|
Bacheo y Refuerzos de 0,05 m. |
42 |
2,243 |
1,146 |
1,359 |
1,359 |
|
|
|
|
|
|
|
|
|
49% |
100% |
10/05/95 |
30/06/96 |
8 |
2 |
16 |
35 |
N.Bruzone-Emp.R.N.Nš7(Río Quinto) |
Puente s/Rio Quinto |
1816-L-94 |
|
|
FTN |
|
Adecuac. integral del puente. |
|
386 |
|
390 |
390 |
|
|
|
|
|
|
|
|
|
100% |
100% |
7/03/96 |
7/12/96 |
8 |
5 |
12 |
12 |
Goya - Acceso a Maruchas |
(Km.796 - Km.815) |
4947-L-94 |
|
|
BIRF1A |
|
Bacheo y Refuerzos de 0,05 m. |
19 |
1,859 |
1,492 |
1,189 |
1,186 |
|
|
|
|
|
|
|
|
|
20% |
100% |
10/07/95 |
23/02/96 |
8 |
5 |
11 |
123 |
Rio Miriñay - Emp.R.N.Nš14 |
(Km.184 - Km.214) |
1826-L-94 |
|
|
FTN |
|
Bacheo e imprimación |
30 |
539 |
453 |
0 |
0 |
|
|
|
|
|
|
|
|
|
16% |
100% |
17/05/95 |
17/01/96 |
8 |
5 |
38 |
95 |
Pte. R.Saenz Peña - Tres Isletas |
(Km.1107 - Km.1167) |
13028-18-86 |
|
|
FTN |
|
Bacheo y refuerzo |
63 |
11,429 |
11,154 |
245 |
244 |
|
|
|
|
|
|
|
|
|
2% |
100% |
15/09/87 |
15/05/96 |
8 |
5 |
6 |
95 |
La Tigra - Pcia. Roque Saenz Peña |
km.1074 - 1111 |
288-L-93 |
|
|
BIRF1A |
|
Reconstrucción Total |
37 |
7,843 |
6,924 |
1,632 |
1,631 |
|
|
|
|
|
|
|
|
|
12% |
100% |
17/08/94 |
17/08/96 |
8 |
1 |
3 |
3 |
Trelew - Acc.a Camarones (I Seccion) |
(1461-1538) |
290-L-93 |
|
|
BIRF1A |
|
Bacheo y Lechada |
77 |
4,960 |
4,903 |
494 |
494 |
|
|
|
|
|
|
|
|
|
1% |
100% |
18/11/93 |
18/01/96 |
8 |
5 |
5 |
12 |
Parana - Emp.R.Prov.N 7 |
(457-534) |
306-L-93 |
|
|
BIRF1B |
|
Refuerzos 0,05 m. y 0,08 m. |
78 |
6,037 |
5,968 |
147 |
146 |
|
|
|
|
|
|
|
|
|
1% |
100% |
30/05/94 |
30/05/96 |
8 |
5 |
26 |
12 |
Nogoyá - Crespo |
(Km.333 - Km.401) |
1834-L-94 |
|
|
BIRF1A |
|
Refuerzos 0.05 m. |
68 |
8,501 |
409 |
8,315 |
8,307 |
|
|
|
|
|
|
|
|
|
95% |
100% |
16/08/95 |
5/05/97 |
8 |
5 |
20 |
127 |
Emp. R.N. N° 12-Sauce de Luna (ISecc) |
(Km.64,2 - Km.102,5) |
1841-L-94 |
|
|
BIRF1A |
|
Bacheo y repav. 0.07 m. |
38 |
4,498 |
4,330 |
2,522 |
2,493 |
|
|
|
|
|
|
|
|
|
4% |
100% |
14/06/95 |
31/12/95 |
8 |
5 |
25 |
131 |
Emp. R.P. N° 11 - Crespo |
(Km.9 - Km.41) |
1844-L-94 |
|
|
BIRF1A |
|
Bacheo, Galibo y Carpeta Asf. |
32 |
3,304 |
631 |
3,191 |
3,184 |
|
|
|
|
|
|
|
|
|
81% |
100% |
16/08/95 |
5/07/96 |
8 |
5 |
8 |
18 |
San Salvador - Emp. R.N. Nš 14 |
Km. 206,40 - Km. 241,00 |
4501-L-94 |
|
|
BIRF1B |
|
Fresado y Lechada |
35 |
1,188 |
|
1,212 |
1,211 |
|
|
|
|
|
|
|
|
|
100% |
100% |
8/04/96 |
23/09/96 |
8 |
5 |
42 |
95 |
Limite c/Chaco - Emp.R.N.81 |
Puente s/Riacho Yacare |
326-L-93 |
|
|
FTN |
|
Montaje Puente Met. y Defensas |
0 |
264 |
221 |
34 |
34 |
|
|
|
|
|
|
|
|
|
16% |
100% |
10/09/93 |
31/12/95 |
8 |
4 |
1 |
34 |
Rio Grande - Rio Zora |
San Pedro - San Martin |
335-L-93 |
|
|
BIRF1A |
|
Alteos parciales y pav.asfáltica |
49 |
7,883 |
7,612 |
1 |
0 |
|
|
|
|
|
|
|
|
|
3% |
100% |
28/09/93 |
28/09/95 |
8 |
1 |
7 |
35 |
Acceso Sur a Santa Rosa |
Av. P. Luro-Av. Spinetto |
3749-L-93 |
|
|
FTN |
|
Obra Básica y Carpeta |
9 |
9,876 |
9,019 |
879 |
878 |
|
|
|
|
|
|
|
|
|
9% |
100% |
30/12/93 |
15/11/95 |
8 |
3 |
12 |
143 |
Limite con La Pampa - Carmensa |
Cochicó - Puesto Arce |
4510-L-94 |
|
|
BID |
|
Reconstrucción y ensanche |
33 |
5,546 |
2,636 |
3,950 |
2,930 |
|
|
|
|
|
|
|
|
|
52% |
100% |
26/05/95 |
31/03/96 |
8 |
5 |
24 |
14 |
Leandro N. Alem - Dos de Mayo |
(Km. 846,43-Km. 952,89) |
1870-L-94 |
|
|
FTN |
|
Reacondic. Banquinas |
106 |
618 |
434 |
252 |
252 |
|
|
|
|
|
|
|
|
|
30% |
100% |
22/05/95 |
31/05/96 |
8 |
4 |
8 |
34 |
Emp.R.Nac.50 - Emp. R Nac. 81 |
(1329-1398) |
401-L-93 |
|
|
BIRF1A |
|
Refuerzos 0,05 m. |
69 |
3,977 |
3,444 |
747 |
508 |
|
|
|
|
|
|
|
|
|
13% |
100% |
14/01/94 |
20/02/96 |
8 |
3 |
10 |
147 |
San Isidro - La Chañarienta |
Km. 849 - Km. 934 |
4500-L-94 |
|
|
BIRF1A |
|
Bacheo y refuerzos conc.asf. |
85 |
1,558 |
949 |
1,470 |
1,469 |
|
|
|
|
|
|
|
|
|
39% |
100% |
17/07/95 |
11/06/96 |
8 |
3 |
9 |
148 |
Emp. R.P. N° 11 - Mercedes |
(Km.753 - Km756) |
1890-L-94 |
|
|
FTN |
|
Refuerzos. de 0.07 m. |
4 |
356 |
|
454 |
360 |
|
|
|
|
|
|
|
|
|
100% |
100% |
14/05/96 |
31/07/96 |
8 |
1 |
10 |
3 |
Caleta Olivia - Fitz Roy |
(1896,75-1972,91) |
428-L-93 |
|
|
BIRF1B |
|
Repar.parc.Base,Bacheo y Lechada |
76 |
3,652 |
2,557 |
1,113 |
1,113 |
|
|
|
|
|
|
|
|
|
30% |
100% |
25/04/94 |
31/01/96 |
8 |
1 |
13 |
3 |
Fitz Roy - Tres Cerros |
(Km1973- Km.2100) |
1893-L-94 |
|
|
FTN |
|
Bacheo y Lechada |
127 |
3,020 |
639 |
2,766 |
2,765 |
|
|
|
|
|
|
|
|
|
79% |
100% |
2/05/95 |
31/03/96 |
8 |
2 |
15 |
A008 |
Av. Uriburu - A° Saladillo Sur |
(Km.15 - Km.25) |
1894-L-94 |
|
|
FTN |
|
Reparación Losas |
10 |
594 |
505 |
279 |
259 |
|
|
|
|
|
|
|
|
|
15% |
100% |
9/05/95 |
31/05/96 |
8 |
4 |
10 |
9 |
Acc. a Santo Domingo- Sgo. del Estero |
(965-1130) |
444-L-93 |
|
|
BIRF1A |
|
Bacheo y sellado |
165 |
3,112 |
2,951 |
6 |
6 |
|
|
|
|
|
|
|
|
|
5% |
100% |
9/03/94 |
9/07/95 |
8 |
1 |
31 |
C/a |
Emp. R.N. 3 - Ea. María Luisa |
(Km. 0-Km. 79) |
1906-L-94 |
|
|
FTN |
|
Alteo, Enripiado y Alcantarillado |
79 |
188 |
|
188 |
0 |
|
|
|
|
|
|
|
|
|
100% |
100% |
15/05/95 |
10/01/96 |
8 |
1 |
29 |
C/b |
Emp. R.N. 3 - C°. Radman |
(Km. 0-Km. 71) |
1907-L-94 |
|
|
FTN |
|
Alteo, Enripiado y Alcantarillado |
71 |
83 |
|
83 |
0 |
|
|
|
|
|
|
|
|
|
100% |
100% |
15/05/95 |
10/01/96 |
8 |
1 |
30 |
C/j |
Emp. R.N. C/k - Río Moat |
(Km. 30-Km. 91) |
1908-L-94 |
|
|
FTN |
|
Obras varias y enripiado |
61 |
311 |
|
100 |
6 |
|
|
|
|
|
|
|
|
|
100% |
100% |
15/05/95 |
10/01/96 |
8 |
4 |
13 |
38 |
Concepción - Faimallá |
Km.738 A Km.766 |
6198-L-93 |
|
|
FTN |
|
Tratamiento Simple |
38 |
1,862 |
1,608 |
261 |
261 |
|
|
|
|
|
|
|
|
|
14% |
100% |
2/05/94 |
2/03/96 |
8 |
2 |
13 |
178 |
Lte. c/Buenos Aires - Bigand |
(Km.47 - Km.87) |
1899-L-94 |
|
|
FTN |
|
Bacheo y Ca. parciales |
40 |
922 |
|
930 |
912 |
|
|
|
|
|
|
|
|
|
100% |
100% |
11/12/95 |
2/07/96 |
8 |
3 |
15 |
40S |
Malargue - Bardas Blancas |
(Km.330 - Km.350) |
1864-L-94 |
|
|
BIRF1A |
|
Bacheo,ref.borde y carp.co.as. |
19 |
1,261 |
445 |
1,211 |
1,211 |
|
|
|
|
|
|
|
|
|
65% |
101% |
3/08/95 |
26/03/96 |
8 |
PROYECTOS FINALIZADOS EN EL AÑO 1996 |
|
|
|
|
|
|
|
|
|
|
2,259 |
140,051 |
90,376 |
60,616 |
58,802 |
|
|
|
|
|
|
|
|
|
35% |
100% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4,157 |
272,761 |
122,229 |
114,897 |
109,081 |
|
|
|
|
|
|
|
|
|
41% |
86% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Proyectos Globales |
|
|
|
|
|
|
|
|
|
|
|
|
|
101,302 |
82,537 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Otros sin datos |
|
|
|
|
|
|
|
|
|
|
|
|
|
191 |
154 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL PROGRAMA 21 |
|
|
|
|
|
|
|
|
|
|
4,157 |
272,761 |
122,229 |
216,390 |
191,772 |
|
|
|
|
|
|
|
|
|
41% |
86% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CODIGO |
TIPO DE OBRA |
|
|
|
Mejoramiento y enripiado |
CODIGO |
ESTADO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
0 |
Mejoramiento y enripiado |
|
|
|
Tratamientos |
|
A licitar |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
Bacheo y Sellado |
|
|
|
Refuerzos |
|
Publicada |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 |
Bacheo y Lechada |
|
|
|
|
|
Licitada |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
Tratamientos |
|
|
|
Reconstrucción de losas de H |
|
Adjudicada |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
Refuerzos |
|
|
|
|
|
Contratada |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
Reconstrucciones |
CODIGO |
|
|
TIPO DE OBRA |
|
Replanteada |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6 |
Reconstrucción de losas de H |
|
|
|
Obras Nuevas (caminos) |
|
En Ejecución |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 |
Reparación de puentes |
|
|
|
Reparación de puentes |
|
Finalizada sin R.P. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Obras Nuevas (caminos) |
|
|
|
Bacheo y Lechada |
|
Finalizada con R.P. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9 |
Obras Nuevas (puentes) |
|
|
|
Obras Nuevas (puentes) |
|
Paralizada |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
Obras de def. e hidráulicas |
|
|
|
Bacheo y Sellado |
|
Rescindida |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11 |
|
|
|
|
Reconstrucciones |
|
Desestimada |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13 |
|
|
|
|
Obras de def. e hidráulicas |
|
En Reprogramación |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|